The project schedule will be updated as the PER is developed.

 

TASK MONTH / YEAR
Prepare Draft PER March-May 2018
Public Hearings: PER, Environmental and Funding TBD
Final PER completed May 2018
Prepare and submit Grant Application (TSEP) June 15 2018
Notice of Award for funding May 2019
Preliminary Design Fall 2019
Project Bidding Winter/Spring 2020
Construction TBD
Project closeout Late 2020

 

This is a draft schedule and subject to change depending on project development and available funding.